FEMA's Elevation Certificate (EC) is the standard form for documenting a building's elevation information. The current version, released in 2023, is FEMA Form FF-206-FY-22-152 (formerly 086-0-33). It comes with detailed instructions and building diagrams. This guide walks through what each section is for so you can understand the certificate you receive.

Section A: Property information

Identifies the owner, address, legal description, building use, latitude and longitude, photos and the building diagram number. Building diagrams illustrate foundation types, such as slab-on-grade, basement, crawlspace, elevated on piers or with enclosures, so readers know which floor counts as the "bottom floor." Section A also records the square footage and number of flood openings in crawlspaces, enclosures and attached garages.

Section B: Flood Insurance Rate Map information

Lists the NFIP community name and number, county, map panel number and suffix, FIRM index and panel effective dates, flood zone, base flood elevation, and the source of the BFE. It also notes whether the building is in a Coastal Barrier Resources System area.

Section C: Building elevation information (survey required)

The surveyor records elevations of key points relative to a vertical datum, including:

  • Top of the bottom floor (including basement, crawlspace or enclosure)
  • Top of the next higher floor
  • Bottom of the lowest horizontal structural member (V zones)
  • Attached garage slab
  • Lowest elevation of machinery and equipment servicing the building
  • Lowest and highest adjacent grade next to the building

Section D: Surveyor, engineer or architect certification

A licensed professional signs and seals the certificate, certifying the elevation data.

Section E: Building measurement information for Zone AO and Zone A without BFE (survey not required)

For these zones, heights above highest and lowest adjacent grade can be measured without a full survey. If the EC supports a Letter of Map Change, Sections A, B and C are needed.

Section F: Property owner certification

The owner or authorized representative signs here when they've completed Sections A, B and E for Zone A without BFE or Zone AO.

Section G: Community information

The local floodplain official may complete or correct information and record permit details, such as permit number, date of certificate of occupancy, and whether the work was new construction or substantial improvement.

Section H: First floor height for all zones (survey not required, insurance purposes only)

New with the 2023 edition, Section H lets the property owner, an authorized representative or a local official record the building's first floor height above the lowest adjacent grade, to the nearest tenth of a foot, using the foundation type diagrams. This supports Risk Rating 2.0, which uses first-floor height as a rating factor. Where surveyed elevations in Section C exist, they take precedence.

Tips

  1. Confirm the building diagram matches your foundation; mistakes affect rating.
  2. Check that the map panel and BFE reflect the current effective FIRM.
  3. Make sure flood opening counts and sizes are recorded if you have a crawlspace or enclosure.
  4. Keep the photos current; they verify the building described.

For context on when and why you need an EC, read elevation certificates explained.

Have questions about how this applies to your property? Get a free flood quote and an agent can walk you through it.

Frequently asked questions

Can I complete any part of the elevation certificate myself?

In Zone AO and Zone A areas without a base flood elevation, Section E can be completed by the property owner, owner’s representative or local official. Sections requiring surveyed elevations need a licensed professional.

What does Section G cover?

Section G is completed by community officials.

Get a free flood quote

Compare NFIP and private flood insurance for your property in minutes. No obligation.

Get a Free Flood Quote